Call Before You Dig
Have Your Utilities Marked
All digging on the Stanford University campus (utilities excavations, tent staking, construction, etc.) requires a call to Underground Service Alert:
- Underground Service Alert (USA) must be called at least (2) two days prior to digging on the Stanford campus.
- Every person planning to dig (or penetrate the ground) should call USA.
Making a Request to USA North (811 / 9-811)
Before You Call: Outline Your Digging Site
Prior to calling USA North (local service provider), outline your digging location with white chalk paint or another manner sufficient to enable underground facility members to determine the area of digging to be field marked.
When to Call
Two (2) working days before your planned digging. USA suggest placing calls on Wednesday, Thursday or Friday afternoons (for the following week's requests) to avoid communication delays.
How to Place a Call
- National One-Call #: 811 (9-8-1-1 from on-campus telephones)
- Alternative #: 1-800-227-2600
Questions You Will Be Asked
Please have the following information on hand when you call USA:
Contact Info | • Phone Number and extension • Are you digging in CA, NV or HI? • Begin Date (2 days prior notice) and Begin Time • Your Name • Your Company's Name • Your Company's Mailing Address • City, State, Zip |
Who the Work is Being Done for | • Have you outlined your area with white paint as required? • Work Permit Number (city, county or state) (yes / no) • Foreman of Job • Nature of Work (blasting, boring, drilling, grading, trenching, tunneling and other forms of digging) |
Location of Digging | • County • Place • Address or Description |
Mapbook Page Thomas Brothers | • Grid (if known) |
USA Ticket Number
At the end of your call, you will be given a ticket number referencing your digging number. Hold on to this number in case you need to call USA back.
Your USA number will only be valid for 14 calendar days from the day you called it in. If your digging is continuing past the active 14 calendar day period, call USA back two (2) days prior to the expiration of your ticket.
After the Call
After placing your call, Maps and Records will respond within 2 working days or otherwise make contact with you in case we need additional time. Additional time of two (2) days is needed when projects require Mutual Agreement (projects within 2-feet of an existing utility) or, if we are marking high priority facilities (projects within 10 feet of an existing high priority facility).
If you need to reach us, please contact: Galen Schmidt, (650) 444-5942
USA Response to Your Ticket
In response to your ticket, the USA members will either:
• Provide you with information about their underground facilities
• Advise you that they do not have any underground facilities in conflict with your digging work
After the USA members have field marked their facilities, you are required to notify USA anytime those markings are no longer reasonably visible.
Before Using Power Equipment
Before you use power equipment, expose the underground facilities in conflict by hand. See marking guidelines for hand digging requirements.
More information on Underground Service
USA North 811 Underground Service Alert of Northern California and Nevada
California Excavation Law (pdf)
California Excavation Handbook (pdf)
Call 811 Know what's below. Call before you dig